Vestas: Within EU increased Availability Compensation by 8% by removing ambiguity from SCADA data and improved Downtime Allocation Table ownership and processes.Migration of entire windfarm from Vestasonline buisness to Vestas Online Professional. India V90 V3's installed an improved end to end SCADA > OPC > PI solution feeding into a Houston based control center. Installed KuSAT, wireless system for windfarm. Sector Management implemented to improve safety.
Nordex: N80's - Netherlands - increased availabilty an focusing on maximising scheduled downtime to resolve issues around pitch battery issues and blade integrity. Incorporated SCADA data system sets into refinery PI system for operational monitoring.
Suzlon: Complete large windfarm install in India and China resulting in improved uptime and resolution of issues with local electrical supply companies. 99.999% uptime and on-line integration of legacy utility meter systems into realtime European PI system. Assisted development of decentralized SCADA system.
LIDAR: Worked with NaturalPower to install onshore and offshore LIDAR units using Directional sat system, GSM and IRIDIUM communication systems.

And many others...


 
A profitable supply chain is about more then just consolidation...   How can SCADA data be used to generate revenue in availability compensation?   Communication with remote sites in high wind - what is the best solution?   What works for accurate prediction? Is Condition Monitoring as good as it promises?   What part of the wind farm do you need to focus on first?